When must you notify the NRC in writing following a failed leak test?

  1. Within 10 days

  2. Within 7 days

  3. Within 14 days

  4. Within 5 days

The correct answer is: Within 5 days

The requirement to notify the NRC in writing following a failed leak test is outlined in the regulations concerning the management of sealed sources and devices. In this context, if a leak test indicates that a source has released radioactive material above the specified limit, a written notification must be provided to the NRC promptly. The correct timeframe for this notification is within 5 days. This short timeframe is crucial because it ensures swift action can be taken to address any potential safety concerns associated with the leakage of radioactive material, minimizing the health risks to workers and the public. The direct and prompt communication with the NRC also allows for timely compliance with regulatory requirements, which is essential in maintaining safety and accountability in handling radioactive materials. Understanding the specific timeframes required for notifications in nuclear regulatory practices emphasizes the importance of regulatory compliance and the urgency of addressing safety issues in a field as critical as industrial radiography.